project
PROJECT
CATEGORIES
Projects
undertaken by VDOT vary in size, complexity, and risk; therefore, a one-size
fits all approach
to
project management is unsuitable. Hence, a project ranking system has been
defined to group
projects
by category based primarily on level of complexity and risk. The categorization
of projects
allows
for a statewide consistent approach to scheduling and to ensure that the
appropriate
scheduling
provision is applied. This is necessary to ensure that the appropriate level of
scheduling
efforts
needed to establish and maintain schedule control on the project is applied.
Project
Category – Level of Complexity and Risk
The
VDOT project ranking system consists of six categories representing varying
levels of complexity
and
risk ranging from very low to very high. Category M is the lowest, which
represents typical
maintenance
projects and schedule type work. Categories I through V represent typical
construction
projects
ranging from simple to very complex. Characteristics of each project category
are described
as
follows:
¾
Raised pavement marker installation, lens replacement;
¾
Pavement marking schedules;
¾
Minor Bridge repair (District wide, minor miscellaneous);
¾
Rumble strip installation;
¾
Slope slide repair, scour repair;
¾
Ground mounted sign maintenance/replacement;
¾
Incidental concrete repair;
¾
Pipe culvert rehabilitation;
¾
Bridge cleaning;
¾
Retaining wall/ Sound wall repair;
¾
Signal maintenance & repair (District wide).
C.
Category M Scheduling Requirements – Category M scheduling requirements are
based
on
the basic scheduling information necessary for the Department to coordinate all
work
required
to complete the Contract and to communicate with the public. The schedule
information
will also be used to plan for and manage the Department’s cash flow, resources,
and
traffic. The Category M Schedule of Operations submission requirements are as
follows:
i)
An Initial Plan of Operations in the form of a written narrative to provide a
description
of the overall plan and intended sequence of progress.
ii)
An Initial Schedule of Operations showing in a tabular format, the period of
time
within
which work at each location, route, or segment of Work as delineated in the
contract
will be accomplished. A bar-chart or CPM schedule may be substituted, at
the
contractor’s option.
iii)
Every week, on a day agreed to by the Contractor and the Engineer, the
Contractor
is
required to provide a Two-week Look-ahead (TWLA) schedule to show the detailed
schedule
of work planned for the following two weeks. The TWLA schedule may be
provided
in a tabular or bar-chart format.
v)
Minimal traffic impact or limitations to the Work; and
vi)
Does not include utility adjustments or relocations; and
vii)
Contract does not contain any Special Provisions for special time-related
conditions,
such
as Interim Contract Milestones, A+B Bidding, Insensitive/Disincentive, or Lane
Rental;
and
viii)
Project has no major materials delivery restrictions, environmental impacts, delayed
right-of-way
acquisitions or access, or other similar constraints and restrictions.
On
a case by case basis, certain single-season simple and low risk projects with
estimated
contract
value greater than $1M that generally meet the criteria listed above may
qualify as
Category
I, as determined by the Area Construction Engineer (ACE);
On
a case by case basis, certain Federal Oversight (FO) maintenance projects or
time
sensitive
maintenance projects with traffic impact may qualify as Category I, as
determined
by
the ACE. Such projects may include concrete pavement repairs or overlay work on
major
corridors
or certain relatively complex time sensitive maintenance projects that are
involved
with
major construction or improvement projects. In such cases, the ACE should
consult with
the
State Construction Scheduler for concurrence.
B.
Examples of Category I Projects – The following are typical Category I
projects:
¾
Retaining wall installation or extensive repair;
¾
Minor bridge substructure repairs (with traffic impact);
¾
Bridge painting (multiple locations or with traffic impact);
¾
Minor urban reconstruction & improvement (could include curb & gutter
and
sidewalks;
new or extended turn lanes);
¾
Surface reclamation, sub-grade stabilization & overlays;
¾
Bridge steel repair (with traffic impact);
¾
Signal installation – Site specific (w/o intersection improvements, no regional
on-call
installations);
¾
Overhead sign installation & lighting installations (multiple locations
& or significant
amount
of lighting);
¾
Simple concrete pavement repair and/or asphalt overlay (major corridor, minimum
traffic
impact).
C.
Category I Scheduling Requirements – Category I scheduling requirements are
based
on
the basic scheduling information needed to communicate the Contractor’s work
plan and
to
assess progress of the Work. The schedule information will also be used to plan
for and
manage
the Department’s resources, expenditures, traffic, as well as to communicate
with
the
general public. The Category I Progress Schedule submission requirements are as
follows:
i)
A written Baseline Progress Schedule Narrative describing the contractors
initial
proposed
sequence and work plan.
ii)
A Baseline Progress Schedule showing in a tabular format, the times within
which the
individual
activities that make up the project will be accomplished. A bar-chart or
CPM
schedule may be substituted, at the contractor’s option.
iii)
A Progress Earnings Schedule (Form C-13C) to show the planned progress for each
month
in terms of percent complete. Percent complete is based on cumulative
anticipated
earnings relative to the total contract value.
iv)
A two-week look-ahead schedule due every week to show the detail schedule for
work
planned for the following two weeks.
v)
A revision of the Baseline Progress Schedule is required when the schedule has
been
significantly
impacted by a change in the Work or condition or the contractor has
deviated
significantly from his baseline plan or schedule.
A.
Criteria for Category II Projects – Category II projects must generally meet
the following
criteria:
i)
Contract duration of one construction season or less (may be two construction
seasons,
but involve simple linear or repetitive operations); or
ii)
Estimated contract value generally less than $3 million; and
iii)
Limited number of straightforward contiguous or linear operations; and
iv)
Low to medium traffic impact; and
v)
Typical conditions and limitations to the work; and
vi)
May include minimal utility adjustments; and
vii)
Contract does not contain Special Provisions for special time-related
conditions, such
as
Contract interim milestones, Incentives/Disincentives, A+B bidding, or Lane
Rental,
etc.; and
viii)
Project has no major materials delivery restrictions, environmental impacts,
right-ofway
acquisitions,
or other similar constraints and restrictions.
On
a case by case basis, certain slightly complex and low to medium risk projects
with
estimated
contract value over $3M that generally meet the criteria listed above may
qualify
as
Category II, as determined by the ACE.
On
a case by case basis, certain high-volume Federal Oversight (FO) maintenance
projects or
relatively
complex maintenance projects that involve multiple items of work, multiple
schedule
constraints, or significant traffic impact may qualify as Category II, as
determined
by
the ACE. Such projects may include concrete pavement repairs or overlay work on
major
corridors
or certain relatively complex time sensitive maintenance projects that are
involved
with
major construction or improvement projects. In such cases, the ACE should
consult with
the
State Construction Scheduler for concurrence.
B.
Examples of Category II Projects –
The
following are typical Category II projects: ¾ Urban grade, drain, & pave
projects of low to medium complexity, ¾ Rural new construction or
reconstruction grade separation roadway and bridge projects (low to medium size
and complexity), ¾ Complex reconstruction and improvements, including widening
and multiple turn lanes that may include utility adjustments and ¾ Major bridge
substructure repairs (with low to medium traffic impact).
¾
Bridge deck replacements, such as multi-span or over railroads;
¾
Major bridge deck repair & concrete overlay (multi-span or over railroads);
¾
Intersection improvements with lighting and/or signal installation;
¾
Bridge & drainage structure replacements (frequently single span with
limited
approach
work);
¾
Major drainage improvements;
¾
Complex concrete pavement repair and/or asphalt overlay (major corridor,
significant
traffic
impact);
¾
Multi-season bridge painting (with low to medium traffic impact).
C.
Scheduling Requirements for Category II – As the amount of work, project duration,
or
level
of complexity and associated risks increases, a scheduling tool that can
graphically
depict
the sequence and timing of the activities in a time-scale format is required to
effectively
communicate the Contractor’s plan of operations and the intended sequence of
progress.
The Category II Progress Schedule submission requirements are as follows:
i)
A written Baseline Progress Schedule Narrative describing the contractors
initial
proposed
sequence and work plan.
ii)
A Baseline Progress Schedule showing in a bar-chart format, the times within
which
the
individual activities that make up the project will be accomplished. A CPM
schedule
may be substituted, at the contractor’s option.
iii)
A Progress Earnings Schedule (Form C-13C) to show the planned progress for each
month
in terms of percent complete. Percent complete is based on cumulative
anticipated
earnings relative to the total contract value.
iv)
A monthly update of the Progress Schedule and Progress Earnings Schedule is
required
to show the actual progress and the current plan to complete the remaining
work.
v)
A revision of the Baseline Progress Schedule is required when the schedule has
been
significantly
impacted by a change in the Work or condition or the contractor has
deviated
significantly from his baseline plan or schedule.
A.
Criteria for Category III Projects – Category III projects must generally meet
the
following
criteria:
i)
Med-size projects with contract duration generally spanning 2-3 construction
seasons;
or
ii)
Estimated contract value generally between $3M and $10M; and
iii)
Limited number of concurrent work-paths; and
iv)
Medium limitations to the work and traffic impact; and
v)
Limited number of utility adjustments; and
vi)
Contract does not contain Special Provisions for special time-related
conditions, such
as
Contract interim milestones, Incentives/Disincentives, A+B bidding, or Lane
Rental,
etc.; and
vii)
Project has no major materials delivery restrictions, environmental impacts,
right-ofway
acquisitions,
or other similar constraints and restrictions.
On
a case by case basis, certain moderately complex and medium risk projects with
estimated
contract value over $10M that generally meet the criteria listed above may
qualify
as
Category III, as determined by the ACE.
On
a case by case basis, certain high-volume Federal Oversight (FO) maintenance
projects or
relatively
complex maintenance projects that involve multiple items of work, multiple
schedule
constraints, and/or significant traffic impact may qualify as Category III, as
determined
by the ACE. Such projects may include major concrete pavement repairs or
overlay
work on major corridors or certain relatively complex time sensitive
maintenance
projects
that are involved with major construction or improvement projects. In such
cases,
the
ACE should consult with the State Construction Scheduler for concurrence.
B.
Examples of Category III Projects –
The
following are typical Category III projects: ¾ Intersection improvements,
including widening and multiple turn lanes with utilities, lighting and/or
signal installation (with medium complexity and traffic impact), ¾ New
roadway/bridge construction or extension projects (medium size, complexity, and
traffic impact), ¾ Bridge deck replacements (multi-span, medium traffic impact)
and ¾ Bridge reconstruction/widening projects (medium size, complexity, and
trafficimpact).
C.
Scheduling Requirements for Category III – As the number of operations or level
of
complexity
and associated risks grow a scheduling tool that allows for adequate planning
and
scheduling
of multiple concurrent activities with considerations for associated project
constraints
is needed to execute and control the Work. Such scheduling method will require
that
sufficient details and activity relationships are added to establish
inter-dependencies
between
related activities to form network paths, with which the activities are
scheduled.
This
is necessary to aid the project staff in efficiently planning and managing the
Work and
available
resources. It is also necessary that the project critical path and the minimum
time
needed
to complete the project are established. The Category III Progress Schedule
submission
requirements are as follows:
i)
A Preliminary Progress Schedule to provide a start-up schedule to execute and
monitor
the Work for the first sixty (60) calendar days.
ii)
A written Baseline Progress Schedule Narrative describing the contractors
initial
proposed
sequence and work plan.
iii)
A Baseline Progress Schedule showing in a CPM format, the times within which
the
individual
activities that make up the project will be accomplished.
iv)
A Baseline Progress Earnings Schedule (Form C-13C) to show the planned progress
for
each month in terms of percent complete. Percent complete is based on
anticipated
earnings relative to the total contract value.
v)
A monthly update of the Progress Schedule and Progress Earnings Schedule is
required
to show the actual progress and the current plan to complete the remaining
work.
vi)
A revision of the Baseline Progress Schedule is required when the schedule has
been
significantly
impacted by a change in the Work or condition or the contractor has
deviated
significantly from his baseline plan or schedule.
relative
complexity that include provisions for special time-related constraints or
conditions as
described
below.
A.
Criteria for Category IV Projects – Category IV projects must generally meet
the
following
criteria:
i)
Medium to large size projects with contract duration generally spanning 3 or
more
construction
seasons; or
ii)
Estimated contract value generally between $10M and $75M; or
iii)
Contract contain Special Provisions for special time-related conditions, such
as
Contract
interim milestones, Incentives/Disincentives, A+B bidding, or Lane Rental,
etc.;
and
iv)
Multiple concurrent work-paths; and
v)
Complex construction staging, phasing, or MOT issues; and
vi)
Complex constructability issues; and
vii)
Substantial traffic impact and limitations to the work; or
viii)
May include major utility relocation/adjustments; and
ix)
Project has no major materials delivery restrictions, environmental impacts,
right-ofway
acquisitions,
or other similar constraints and restrictions.
On
a case by case basis, certain relatively complex and high risk projects with
estimated
contract
value less than $10M that generally meet the criteria listed above may qualify
as
Category
IV, as determined by the ACE. In such cases, the ACE should consult with the
State
Construction
Scheduler for concurrence.
On
a case by case basis, certain relatively complex and high risk projects with
estimated
contract
value over $75M that generally meet the criteria listed above may qualify as
Category
IV, as determined by the ACE.
B.
Examples of Category IV Projects projects: ¾ Major urban intersection
improvements, including widening and multiple turn lanes with utilities,
lighting and/or signal installation (medium to large size, complex, and significant
traffic impact), ¾ Rural/Urban new construction or reconstruction grade
separation roadway and bridge projects (medium to large size, complex, major
corridor), ¾ Major bridge deck replacements (substructure repairs, multi-span,
multi-lane, major corridor, with significant traffic impact) and ¾ Major bridge
& drainage structure replacements (multi-span with extensive approach
work).
¾
Major widening projects (medium to large size and complexity, major corridor,
with
significant
traffic impact).
C.
Scheduling Requirements for Category IV – As the size, complexity, and
associated
risks
grow, a scheduling tool that allows for adequate planning and scheduling of
multiple
concurrent
operations is needed to execute and control the Work. For such projects, a tool
that
allows for an accurate assessment of the reasonableness of the schedule and
current
status
of the activities and the project based on costs is also needed to control the
project
and
to manage schedule-related risks on the project. The Category IV scheduling and
Progress
Schedule submission requirements are based on the Category III requirements
with
additional
requirements as described below:
i)
A Preliminary Progress Schedule to provide a start-up schedule to execute and
monitor
the Work for the first ninety (90) calendar days.
ii)
A written Baseline Progress Schedule Narrative describing the contractors
initial
proposed
sequence and work plan.
iii)
A cost-loaded Baseline Progress Schedule showing in a CPM format, the times
within
which
the individual activities that make up the project will be accomplished. The
cost-loaded
schedule will be used to generate the time-distributed cost data on
which
the Progress Earnings Schedule is based.
iv)
A Baseline Progress Earnings Schedule (Form C-13CPM) based on time-distributed
cost
data generated from the cost-loaded schedule to show the planned progress for
each
month in terms of percent complete. Percent complete is based on anticipated
earnings
relative to the total contract value.
v)
A 30-day look-ahead schedule to depict work planned for the next period.
vi)
A monthly update of the Progress Schedule is required to show the actual
progress
and
the current plan to complete the remaining work.
vii)
A revision of the Baseline Progress Schedule is required when the schedule has
been
significantly
impacted by a change in the Work or condition or the contractor has
deviated
significantly from his baseline plan or schedule.
A.
Criteria for Category V Projects – Category V projects must generally meet the
following
criteria:
i)
Very large projects with contract duration generally spanning 3 or more
construction
seasons;
or
ii)
Estimated contract value generally greater than $75M; and
iii)
Contract contain Special Provisions for special time-related conditions, such
as
Contract
interim milestones, Incentives/Disincentives, A+B bidding, or Lane Rental,
etc.;
and
iv)
Considerable number of concurrent work-paths; and
v)
Complex construction staging, phasing, or MOT issues; and
vi)
Complex constructability issues; and
vii)
Substantial traffic impact and limitations to the work; and
viii)
Substantial number of right-of-way acquisitions and/or relocations; or
ix)
Major material delivery restrictions; or
x)
Significant utility relocation/adjustments; or
xi)
Major environmental or community impact.
On
a case by case basis, certain relatively complex and very high risk projects
with estimated contract value less than $75M that generally meet the above
listed criteria may qualify as Category V.
as determined by the ACE. In such cases, the
ACE should consult with the State
Construction
Scheduler for concurrence.
B.
Examples of Category V Projects –
On
a case by case basis, certain relatively complex and very high risk projects
with estimated contract value less than $75M that generally meet the above
listed criteria may qualify as Category V.
The
following are typical Category V projects: ¾ Major rural/urban new construction
or reconstruction grade separation roadway and bridge projects (large size,
complex, major corridor, significant traffic impact), ¾ Major widening projects
(large size, complex, major corridor, significant traffic impact), ¾ Major
interchange projects (large size, complex, major corridor, significant traffic
impact),
¾ Major bridge deck replacement projects (large size or multiple bridges,
complex,major corridor, significant traffic impact).
¾
Individual Category III or IV level projects that are included in
multiple-contract
mega-projects
like Woodrow Wilson, Springfield Interchange, etc.).
C.
Scheduling Requirements for Category V – As the size, complexity, and
associated risks
grow,
a scheduling tool that will allow for adequate planning and scheduling of
multiple
concurrent
operations, projects, manpower, equipment, and expenditures is required to
accomplish
the Work. Such scheduling tool should also allow for an accurate assessment of
the
status of the individual activities and the project; as well as progress of
selected major
operations
that will have the greatest influence on the schedule.
The
Category V scheduling and Progress Schedule submission requirements are based on
the
Category
IV requirements with additional requirements as described below:
i)
A qualified and dedicated project scheduler/coordinator to coordinate all
scheduling
meetings
and issues.
ii)
Contractor’s working on a Category V project will be required to develop and
maintain
their schedules in a collaborative environment within the VDOT scheduling
database.
iii)
A written Baseline Progress Schedule Narrative describing the contractors
initial
proposed
sequence and work plan.
iv)
A Preliminary Progress Schedule to provide a start-up schedule to execute and
monitor
the Work for the one hundred and twenty (120) calendar days.
v)
A cost-loaded and resource-loaded Baseline Progress Schedule showing in a CPM
format,
the times within which the individual activities that make up the project will
be
accomplished. The cost-loaded schedule will be used to generate the
timedistributed
cost
data on which the Progress Earnings Schedule is based.
vi)
A Baseline Progress Earnings Schedule (Form C-13CPM) based on time-distributed
cost
data generated from the cost-loaded schedule to show the planned progress for
each
month in terms of percent complete. Percent complete is based on anticipated
earnings
relative to the total contract value.
vii)
A Commodity Progress Report (Form C-13COM) to show the anticipated progress of
selected
items of work, whose rate of progress will have the greatest influence on
the
schedule.
viii)
A weekly four-week look-ahead schedule detailing work planned for the next four
weeks.
ix)
A monthly update of the Progress Schedule is required to show the actual
progress
and
the current plan to complete the remaining work.
x)
A revision of the Baseline Progress Schedule is required when the schedule has
been
significantly
impacted by a change in the Work or condition or the contractor has
deviated
significantly from his baseline plan or schedule.
Comments
Post a Comment