D OUT MORE ABOUT THE IDEA BEHIND THE TRANSLEX-PRINCIPLES
D
OUT MORE ABOUT THE IDEA BEHIND THE TRANSLEX-PRINCIPLES
No. VI.1 - Termination of contract in case of
fundamental non-performance
(a) If a party's failure to perform its obligation
amounts to a fundamental non-performance, the other party may terminate the
contract.
(b) The right of a party to terminate the contract
is exercised by notice to the other party.
(c) If performance has been offered late or
otherwise does not conform to the contract the aggrieved party will lose its
right to terminate the contract unless it gives notice to the other party
within a reasonable time after it has or ought to have become aware of the
offer or of the non-conforming performance.
(d) Termination of the contract releases both
parties from their obligation to effect and to receive future performance.
(e) Upon termination of the contract either party
may claim restitution of whatever it has supplied, provided that such party
concurrently makes restitution of whatever it has received. If restitution in
kind is not possible or appropriate allowance should be made in money whenever
reasonable. However, if performance of the contract has extended over a period
of time and the contract is divisible, such restitution can only be claimed for
the period after termination has taken effect.
(f) Termination does not preclude a claim for
damages for non-performance.
(g) Termination does not affect any provision in the
contract for the settlement of disputes or any other term of the contract which
is to operate even after termination.1 Introduction
2 Breach of contract3 Frustration4 Convenience5
Others6 Rescission7 Suspension8 Determination9 Related articles on Designing
Buildings Wiki
Introduction
Most forms of contract will include
termination clauses, setting out the circumstances
under which a contract may be terminated. When a contract is terminated, the
parties to the contract are no longer obliged to perform their obligations
under the contract.
Terminating a contract can be complex, and it is
very important that the correct procedures are followed. This may involve
issuing notices setting out the
grounds for termination , allowing warning periods,
and giving the opportunity to remedy breaches.
There are a number of reasons why one or both
parties to a contract may seek to terminate the contract .
Breach of contract
If the one of the parties to a contract fails to
perform as required by the
contract , this may constitute a breach of contract
. If the breach of contract is serious (a material breach), then the innocent
party may also consider that it is discharged from any further obligations
under the contract .
Where one party behaves in such a way as to indicate
that it no longer intends to accept its obligations under thecontract , this is
considered to be a repudiatory beach (or fundamental breach), allowing the
innocent party to terminate the contract and to sue for damages . Generally,
the contract will set out what those breaches are, but they might include:
Refusal to carry out work . Abandoning the site. Removing
plant from the site . Failure to make payments .
Employing others to carry out the work . Failure to
allow access to the site . Failure to proceed regularly and diligently .Failure
to remove or rectify defective works . Where repudiation is considered to have
occurred, the innocent party can either affirm that the contract will continue,
or accept the repudiation and so terminate the contract . In either case, they
will have the right to claim damages . Either way, it is important that there
is some sort of response, as inaction may be considered to be an affirmation of
the contract .
Assessing the seriousness of breaches of contract
depends on the particular circumstances and terms of the
contract . For example, if a contractor failed to
carry out the work to an agreed timetable, this might be considered a
relatively minor issue on some projects , whilst on others it could be an
extremely serious breach . The innocent party must be careful therefore to
establish that there has actually been a material breach before considering
that the contract is terminated, otherwise they might find themselves in breach
of contract .
This can lead to disputes, where for example, the
client refuses to make
payment, claiming that the contractor has failed to
perform, whereas the
contractor contends that they are not performing
because the client has refused to make payment.
An anticipatory breach (or anticipatory repudiation)
occurs when one of the parties to the contract declares to the other that they
do not intend to perform their obligations under the contract .
Frustration
Frustration occurs when circumstances that are not
the fault of either party mean it is impossible to continue with the contract .
The contract will come to an end without any party being considered to be in
breach . However, parties must be certain that a frustration event has occurred
so as not to be in
breach of contract .
Force majeure provisions might provide for
circumstances that could otherwise be considered frustration events, and so
result in termination of the contract .
Force majeure (for example,
exceptionally adverse weather conditions) is
generally considered a
relevant event in construction contracts which will
allow for an extension of time and a claim for loss and expense rather than
termination . This may be in the interests of both parties.
For more information, see Frustration .
Convenience
Contracts may allow termination for ‘convenience’.
This can be useful for example if the client fails to secure sufficient funding
for the project to proceed. However termination for convenience can leave the
terminating party open to significant claims by the other party.
Termination for convenience is only provided for in
some forms of contract , and is often only available to the client .Others
Contracts may also allow termination under specific
circumstances peculiar to a particular project. They may also allow termination
for insolvency or bankruptcy.
Rescission
Rescission is a process of returning both parties to
the position they would have been in had they not entered into a
contract . This might be appropriate for example if
there is a serious error in the contract .Suspension
Contracts may also allow suspension of performance.
The circumstances allowing suspension are generally similar to those allowing
termination . Suspension can be useful, for example, if the client has
difficulty in raising funds to pay for the work to proceed at the speed
anticipated by the contract . In addition, the Housing Grants Construction and
Regeneration Act gives the right to suspend performance for failure to make
payment that has been notified as due.
Either party may have the right to terminate at the
end of a suspension period, or if a suspension becomes prolonged with no
prospect of work re-commencing.
See Suspension of performance for more information.
Determination Determination ends the contractor 's
obligations under the contract , but the contract remains in place, as do the
rights of both parties.
See Determination for more information.
Related articles on Designing Buildings Wiki
Alternative dispute resolution .Breach of contract
.Concurrent delay .Consequential losses .Construction Act.Defects
.Determination .Extension of time .Force majeure.Fair payment practices
.Frustration .Liquidated damages .Loss and expense .Repudiation .Suspension of
performance.
Variations.
Contract Clauses
2 The right to terminate the contract requires that
the other party's non-performance in fundamental. The type of non-performance
is irrelevant, it relates to any failure by a party to perform any of its
obligations under the contract. This wide scope includes defective and late
performance.
A party's non-performance is fundamental if the
requirements of Art. 25 CISG are met, i.e . if the non-performance
substantially deprives the other party of what it was entitled to expect under
the contract unless the non-performing party did not foresee and could not
reasonably have foreseen such result. The nature of the obligation which one
party is not performing may also be relevant in determining whether that
party's non-performance is fundamental, e.g . when strict performance in
compliance with the letters of the contract is of the essence. The time factor
may also be relevant in that a non-performance that, in and of itself, is not
fundamental, may be qualified as fundamental because the non-performance is of
such a nature that the other party has reasonable grounds to believe that the
non-performing party will not or cannot perform in the future.
Please cite as: "Comme
Dentons - Gary Smith What is a
"reasonable" notice period when the contract is silent?
What is a "reasonable" notice period when
the contract is silent?
This was the question that came before Mr Justice
Norris towards the end of 2013 in the case of Hamsard 3147 Limited trading as
"Mini Mode Childrenswear", JS Childrenswear Limited (in liquidation))
v. Boots UK Limited.
Background
This case arose following the insolvency of the
supplier of the "Mini Mode" clothing brand to Boots stores throughout
the United Kingdom. However, the principles laid down are of universal
application to a question that arises on many occasions – what is a
"reasonable" notice period if the contract is silent on this point?
The reasons for this silence can range from the parties failing to address the
issue up front to, as was the case here, circumstances having intervened
between the parties leading to a renegotiation of the original agreement
leaving the notice period position somewhat unclear.
Judgment
In his judgment, Norris J set out the following
principles to be applied when deciding whether a notice period given is
"reasonable":
1. what length of notice is reasonable must always
depend on the particular facts of the particular case – other cases on this
issue are therefore of limited assistance;
2. the particular facts might well involve
consideration of the general circumstances and practices of the trade in which
the claimant and the defendant are involved, since that relevant background
might assist the objective observer to understand what the parties may
reasonably be understood to have agreed as to being "reasonable
notice";
3. what is "reasonable notice" is to be
judged at the time when the notice is given – indeed as Norris J said, quoting
Clarke J in Paper Light Limited v. Swinton Group Limited (1998), "…it
would be unsatisfactory and make no commercial or other sense to hold that the
reasonable period of notice should be determined long before the notice was to
be given." ;
4. the principle that the length of notice to be
given is to be assessed in light of the circumstances obtaining when the notice
is given does not mean that the circumstances at the time of the contract are
irrelevant; and
5. the degree of formality in the relationship will
determine what notice period is reasonable – the more relaxed the relationship
the less likely it is that the law will imply a lengthy notice period.
Applying these principles to the case before him,
Norris J decided that a nine-month period of notice given by Boots to Hamsard
was indeed reasonable.
Additional arguments
Does affirmation of a contract by one party where
there has been a repudiatory breach by the other party constitute a waiver of
those breaches for the purposes of deciding what notice period is
"reasonable"?
Counsel for Hamsard claimed that, whilst his client
was in repudiatory breach of the contract, once Boots decided to affirm the
contract and terminate it by notice Hamsard's repudiatory breaches were
irrelevant and could not be taken into account in deciding what period of
notice was reasonable. This argument was rejected by Norris J, who stated that
affirmation of the contract is not the same as waiver of the breaches.
Was it relevant in deciding what period of notice
was "reasonable" that the current arrangements would inevitably be
terminated as they were only ever intended to be interim in nature?
Norris J stated that the "notice period cannot
be divorced from the realities of operating the contract" . Accordingly
the fact that the termination of the interim arrangements had been discussed
between the parties and that they were preparing for such an event lends itself
to a shorter period of notice as being "reasonable".
Should a term of "good faith" be implied
into the contact when deciding whether a notice period is
"reasonable"?
The original 2007 Agreement between Boots and its
supplier contained a provision that the parties would "… at all times act
in good faith towards one another in relation to the operation of the Agreement
to approach their dealings with one another on an open and collaborative basis
so as to ensure that they maximise the Net Profit generated under the Agreement
…" . While acknowledging that the revised commercial arrangements between
the parties placed the continued existence of the good faith provision in
doubt, counsel for Hamsard argued that the modern approach of the courts was to
consider whether the provision which it is sought to imply into the contract
(namely a provision of good faith dealings between the parties) would spell out
in words what the contract, read against the relevant background, would reasonably
be understood to mean. To support his argument counsel for Hamsard quoted the
decision of Leggatt J in Yam Seng Pte Ltd v. International Trade Corporation
(2013) , in which Leggatt J held that while English law did not recognise a
requirement of good faith as a duty implied by law into all commercial
contracts "…there seems to me to be no difficulty … in implying such a
duty into any ordinary commercial contract based on the presumed intention of
the parties" . Further, counsel for Hamsard sought to classify the
commercial arrangement between Hamsard and Boots as a long term
"relational contract", which had existed since 2002 and which, in the
words of Leggatt J, "…may require a high degree of communication,
co-operation and predictable performance based on mutual trust and confidence
and involve expectations of loyalty which are not legislated for in the express
terms of the contract… ".
While accepting the decision of Leggat J, Norris J
said that the current arrangements were distinguishable on their facts. While
the 2007 Agreement was "a true joint venture which was contemplated to
last for a considerable period and it made appropriate express provision… about
the approach each party should adopt to the relationship … [the] implicit
contract entered into in February 2009 was brought about by force of
circumstance and is plainly an interim arrangement affording the different
parties an opportunity to negotiate a new joint venture ". Indeed, as
Norris J said: "It is not obvious that [the parties] would have intended a
clause about "good faith" directed to the conduct of a long term
joint venture to form part of their interim bargain."
Lessons to be learned
What lessons can be learned from this decision?
Finally, it is clear from the comments of Norris J
on the "good faith" argument that, while he did not rule out its
application in future cases, the implication of a term of "good
faith" in a commercial contract cannot be used to detract a party from
exercising its contractual rights. As Norris J stated, " … I do not accept
that there is to be routinely implied some positive obligation upon a
contracting party to subordinate its own commercial interests to those of the
other contracting party… Boots had a contractual right to terminate the
relationship on reasonable notice. It was free to exercise that right according
to its terms…"Even if a "good faith" term is either expressly
recorded in an agreement or implied by the courts, this term does not
necessarily take precedence over or detract from other commercial terms of the
contract tion contracts
Termination and suspension of construction contracts
This guide was last updated in August 2011.
This guide covers contractual and non-contractual
rights to terminate a construction contract. Contractual rights may include the
right to terminate 'at will' where there has been no breach by the other party.
The majority of standard form building contracts
contain express provisions regulating the rights of either or both parties to
terminate the contract in defined circumstances.
Non-contractual rights to terminate
Frustration: this occurs when neither party has
defaulted on the original contract but other circumstances have intervened to
prevent the contract from being performed as originally intended. The result
must be that further performance of the contract is impossible, illegal or
radically different from what the parties contemplated when they entered into
the contract.
If a frustrating event occurs the contract
automatically ends and the parties are excused from their future obligations,
although any accrued liabilities will remain.
It is important that a party is sure that
frustration has actually occurred if it is going to rely on frustration to
justify ceasing to perform its obligations under the contract to avoid being in
breach if the event is not in fact a frustrating one. Case law gives some
examples of events that are not frustrating events - for example, if the
contract is more expensive to perform this is not a frustrating event. If an
event happens which is provided for in the contract the consequences of that
event happening will be as set out in the contract and it will not be a
frustrating event. Parties therefore need to be wary of the potential overlap
with force majeure clauses .
Repudiation: this occurs when a party commits a
breach of contract that is sufficiently serious that it entitles the innocent
party to treat the contract as terminated with immediate effect and to sue for
damages for breach of contract. Whether a material or anticipatory breach will
depend upon the severity and effect of the breach, and whether it goes to the
root of the contract.
Ordinarily, certain extreme types of breach will
amount to a clear repudiation of a construction contract. Examples include:
refusal to carry out work;
abandonment of the site or removal of plant by the
contractor;
employing other contractors to carry out the same
work;
failure by an employer to give access to the site.
Other breaches may not be clear-cut. If the innocent
party purports to treat the contract as repudiated because of a breach that is
not in fact repudiatory it will have committed wrongful termination and be in
breach itself. For that reason if there is doubt about whether or not a breach
is repudiatory the innocent party may consider exercising a contractual right
to terminate instead if available, although the amount of damages recoverable
would usually be lower than damages for repudiatory breach.
Repudiation by one party will not by itself bring an
end to further contractual obligations - it must be accepted by the innocent
party. There is no particular form that this acceptance must take but it must
be an unequivocal acceptance. If it is accepted, both parties are released from
performance of their respective unperformed obligations and damages, assessed
under the normal rules, will be payable by the party at fault. Damages for
repudiation aim to put the innocent party in the position it would have been in
had the contract been properly completed.
If the innocent party does not accept the
repudiation it 'affirms' the contract. It is still entitled to claim damages
for the breach but the contract will continue.
Difficulties can arise if the innocent party
inadvertently affirms the contract instead of accepting the repudiation by
acting in a way that contradicts acceptance or is equivocal in some way. It may
find itself in breach of contract if it stops performing its obligations in the
mistaken belief that it has accepted the repudiatory breach.
In some cases a breach may give the innocent party
both a right to terminate for repudiation and a right under the contract. The
innocent party does not necessarily have to elect to use one right or the other
in these circumstances, but if exercise of the contractual right is
inconsistent with acceptance of repudiation - for example, if the consequences
of terminating under the contractual right are different - or the response to
the breach is less than unequivocal the innocent party will be taken to have
'affirmed' the contract and will have to rely on the contractual right rather
than repudiation.
Contractual rights to terminate
Termination clauses in contracts give parties right
to terminate in certain circumstances. These most commonly deal with breaches
of specified contractual obligations. There may be rights to terminate in other
situations too, such as the occurrence of a force majeure event.
Termination for convenience
Termination 'at will' or 'for convenience' wording
may be inserted into a contract allowing one party to terminate without having
to establish that some event has occurred or breach has been committed by the
other party. This can be useful where:
the employer reconsiders the use to which land
should be put, cannot secure financing for the whole of the project or cannot
secure anchor tenants'
the contractor finds the project will be
unprofitable or too risky, or the project has been suspended for a significant
period with no prospect of it being recommenced.
This type of provision has been traditionally less
common than those permitting termination for default in some of the unamended
standard forms, but employers are given the right to do so in some forms such
as GCWorks and NEC3 and in the majority of PFI contracts. However, contractors
and consultants are rarely given the right to terminate for convenience.
What does the case law say?
A contract may provide no express limitation on
when, or in what circumstances, a termination for convenience clause can be
operated. However case law tends to suggest that, in the absence of sufficient
wording, it will be a breach of contract to exercise a termination for
convenience clause simply for the employer to obtain a better price to complete
the works from another contractor. The English courts tend to look to
Australian cases for guidance on this issue.
Provide for compensation: to be effective,
termination for convenience clauses will need to provide for contractor
compensation. The standard forms which contain these clauses already do so. An
Australian case in 2000 held that where compensation is provided for in the
contract in clear, unambiguous terms it will usually be enforceable.
Clear wording: as with most contract provisions,
clear wording will be required before a termination for convenience clause will
be fully effective. Unreasonable provisions, such as allowing the employer to
pass work on to a third party, must be stated in clear, unambiguous terms
otherwise they will be unenforceable.
Use of omissions clauses to tackle bad bargains and
poor performance: the courts have decided that an employer will not be able to
use an omissions clause to get out of what it now considers to be a bad
bargain. It is also doubtful that such a clause can be relied on by an employer
to switch contractors in the event of dissatisfaction with the current
contractor's work.
An example of an attempt to do this can be found in
a 2003 case between Abbey Development and PP Brickwork Ltd. Here, the contract
allowed for the employer to reduce or increase the quantity of work offered to
the contractor as well as containing a termination for convenience clause.
Abbey relied on these provisions to remove work from PPB after putting the
contractor on notice for insufficient supervision and poor workmanship. The
judge found that the provision was not clear enough to allow Abbey to use it to
pass the work on to another contractor – it only allowed Abbey to reduce work
where this was no longer required for the completion of the project.
Rational, honest and proper reasons: this was
discussed in another 2003 case between Westminster Council and Hadley Design
Associates. HDA was contracted on a rolling basis to refurbish flats built in
the late 1950s. The Council terminated the contract under a one-month
termination clause that did not require reasons, citing:
the need for market testing driven by a requirement
for compulsory competitive tendering;
their desire to have a single firm supply
maintenance and repair services, having already appointed another firm to
supply maintenance services after the competitive tendering process;
residents' dissatisfaction with HDA's services.
The judge held that these reasons were 'rational,
honest and proper'.
In summary, the case law warns us that even if the
contract does contain an express provision dealing with termination for convenience:
trivial breaches may preclude termination;
harsh objectives need clear wording, otherwise
termination will be seen as an intrusion on the contractor's right to finish
the work;
work transferred between contractors is
questionable;
an employer cannot use an omissions provision to get
out of a bad bargain, and it is also doubtful it can be used if the employer is
dissatisfied with a contractor's performance;
a termination clause should provide for compensation
to avoid being treated as unenforceable because it is unfair.
Suspension
As with termination, suspension can take many forms.
For example, a contractor may wish to respond to actual or alleged breaches of
contract by an employer by suspending works, or an employer may wish to respond
by suspending payment. Suspension clauses in the contract can be very helpful,
but can sometimes be overlooked when the parties' focus has been taken up by
negotiating the termination provisions.
There is a very close relationship between
suspension and termination and, depending on how the clause is drafted, the end
result of a suspension clause may be much the same as a termination clause in
that either party will have the right to terminate the contract at the end of
the agreed suspension period.
The justification for suspension clauses will be
broadly similar to termination – for example, there may be a change of
circumstances on the ground that makes continuing with the works impossible in
the short term. Occasionally suspension can be used by one party to allow it space
to consider how to proceed with a project, which should be acceptable to the
other party if kept within bounds.
In the absence of an express contractual term, it
would be difficult to argue that a general right to suspend exists in law as
the courts have consistently refused to recognise such a right. It is therefore
a good idea for the parties to consider having a suspension clause in their
contracts. If so, they should also ensure that the contract deals adequately
with the immediate practical consequences of a suspension order and how long a
contract can be suspended for before termination may occur. Consideration
should also be given to what happens when works are to resume following
suspension.
Summary
Proceed with caution before using termination and
suspension provisions and, if these rights are to be invoked, make sure you
strictly follow the contract's notice and procedural requirements
Be careful with your wording. If a contract contains
a termination for convenience provision, it is likely that it will be
considered in breach of contract if this is used simply to obtain a better
price from another party to complete the works - even where there is no express
limitation on the circumstances when the provision can be used.
Where no provision is made in the contract for
termination for convenience, it may be appropriate to consider whether any
default or neutral grounds of termination are applicable or appropriate in the
circumstances. Construction contracts
Diversified industrial
Energy EuroFrustration in construction contracts
Share Add a comment
Send us feedback Frustration occurs when
circumstances that are not the fault of either party to a
contract mean it is impossible to continue with the
contract . As a result, the contract comes to an end without either party being
considered to be in
breach . However, the parties must be certain that a
frustration event has occurred so as not to be in breach of contract .
Frustration is a common legal principle, but it is
applied as narrowly as possible by the courts - it does not cover
contracts that were always going to be impossible to
perform. For example, it would not apply in the case of a
contract to construct a tall building that could not
be fulfilled because the
ground conditions were completely unsuitable.
Identifying the contractual obligations of the
parties at the date of the contract is key to being able to establish the
conditions for frustration .
Some events that may lead to a frustrated contract
include:
The government imposing unforeseen restrictions on
building .
Laws being passed that make it illegal to undertake
what was promised under the contract
The building where works were to be carried out
being destroyed.
An event that was crucial for the
contractual obligations being cancelled.
Sometimes a party may try to claim a
contract is frustrated when they are obligated to
make payments in a different currencies which then fluctuates. However, this
does not necessarily amount to frustration .
Events that do not alter the obligations but instead
delay performance, such as a workforce strike, don’t necessarily amount to
frustration . However, it might do should the events have a particularly
serious effect on the obligations or if the delay is particularly long.
Force majeure provisions might provide for
circumstances that could otherwise be considered frustration events, and so
result in termination of the contract . However, generally, force majeure (for
example, exceptionally adverse weather conditions) is considered a relevant
event which construction contracts allow for by an extension of time rather
than termination .
Find out more
Related articles on Designing Buildings Wiki
Breach of contract .
Extension of time .
Force majeure.
Loss and expense .
Relevant event .
Suspension of performance.uction Litigation So
you’ve hit that point where you’re sick to death of dealing with the other
party’s games, and you’re ready to pull the termination trigger.
Before you do, you need to be absolutely sure that
you’re in a solid position to terminate the contract.
Failing to terminate a construction contract
properly can drastically affect your entitlements and your legal position, and
can actually leave you vulnerable to a claim by the other party.
The Usual Principles of Terminating Contracts
Below we deal with terminating contracts using the
formula in the Australian Standard. However, while following that process might
be normal, your common law rights of termination still exist and it’s important
to understand how they work.
What does this mean? It means that a construction
contract can be terminated even without strictly following the process it might
have laid out in its terms.
The only exception here is if the contract clearly
and expressly excludes your common law rights of termination, which is not
usually the case.
The basic common law rights of termination are
fairly straightforward:
1. There must be a breach of a fundamental term of
the contract;
2. You must clearly terminate the contract following
that breach.
As you’d expect though, despite this deceptively
simple statement, most people follow the process in the Contract. This is
because termination under the process in the contract is normally clearer and
less contentious than relying on the common law position.
Because each contract is unique, fully understanding
your contract and how it interacts (if at all) with your ordinary rights of
termination is an essential starting point.
Termination under Australian Standards contracts
The majority of standard contracts, including the
Australian Standards building contracts, contain a formal process for the
parties to follow which can trigger a right to terminate.
The process exists to minimise doubt and dispute
about whether or not a party had a right to terminate. The process does not, of
course, remove the chance of argument entirely.
The more popular Australian Standards contracts
ordinarily contain a procedure where a principal or head contractor, in the
event of a major breach, sends a notice to the contractor or sub-contract to
“show cause”.
Usually the contract itself will set out what’s
required in a show cause notice. However, by and large, the notice will need to
clearly state what the problem is and call upon the other party to either fix
it or say how they are going to fix it in a specified period of time.
‘Show cause’ notice must comply
In order to trigger the right of termination, a show
cause notice must be validly issued under the contract.
However, the Courts have taken a pragmatic view of
in this area, not always requiring technically strict compliance with the
provisions but rather adopting a common sense business approach having regard
to the context.
What if you Don’t ‘show cause’
Having received a show cause notice the contractor
needs to respond to it to the principal’s reasonable satisfaction. Depending on
the context, that might include a plan for rectification, a plan to get back
onto the timetable, and details about how and when that’s going to be achieved.
If the contractor fails to respond or the response
is inadequate, the Principal may, by written notice, either: take out of the
Contractor’s hands the whole or part of the work remaining and suspend payment;
or terminating the contract.
What if the Principal is at Fault?
The standards operate similarly if it’s the
Principal in substantial breach.
The main difference (at least, in some of the AS
contracts) is that the Contractor must first suspend the works before it’s
entitled to terminate.
Determining whether a party in substantial breach
has ‘shown cause’
As we’ve mentioned, once a show cause notice is
issued the party allegedly at fault has to respond to the notice.
Once you receive that response, your obligation is
to give proper and honest consideration to whether the other party has, in
fact, shown cause in response to the notice issued.
That said, Courts have upheld decisions to terminate
even where that decision was unreasonable or purely self-interested by the
innocent party.
This formal procedure is replicated in other
variants of the AS4000 suite of contracts such as the AS 4901-1998 Subcontract
conditions and the AS 4902-2000 General conditions of contract for design and
construct. Similar procedures are also found in other standard form building
contracts.
What If you Terminate Incorrectly?
What happens if you try to terminate but stuff it up
in some way?
Perhaps you don’t issue a valid show cause notice,
or perhaps the issue wasn’t considered a substantial breach? And then, despite
that, you go ahead and issue a termination notice.
The main benefits to terminating a contract when the
other party is at fault are:
1. Obviously, getting another party in to do the
work properly (or getting yourself out of a contract that has become
unprofitable);
2. The ability to claim damages against the other
party.
Failing to terminate properly can kill off both of
these benefits.
How’s that? Well, if you try to terminate but don’t
do it right, it’s generally regarded as a “wrongful repudiation”. That is,
you’ve indicated that you don’t intend to be bound by the contract anymore.
In response to that, the other party can “affirm”
the contract – that is, keep you bound to it – or they can terminate it
themselves.
If they decide to terminate, it’s actually THEM who
get to claim damages and not you.
This can put contractors in a tough situation. Say,
for example, a Principal continually delays giving instructions or appears to
be farming out work inside your scope to other contractors. Have they
repudiated or not? Should you terminate or not?
Making the wrong decision can leave you not only
unable to claim your losses back, but vulnerable to claims being made against
you.
Damages for wrongful termination
So everything’s gone wrong – you tried to terminate
and didn’t get it right, then the other party accepted your repudiation and
terminated the contract themselves.
What can they claim against you?
A principal might, for example, try to claim the
costs of getting a new contractor on the job (including tendering costs), the
additional costs of that contractor coming up to speed, and potentially losses
resulting from the project delay (for example, interest on finance).
A contractor might be able to claim not only for
work done, but also for profits that they will no longer achieve on the job
having been wrongly terminated. They might claim for staff costs and
remobilisation costs, for equipment leases that had to be broken early, or many
other categories.
In each case, all parties have a duty to take
reasonable steps to mitigate (that is, minimise) their losses.
It’s also important to check whether your contract
has provisions that affect your ability to claim for certain types of loss.
Practical Advice on Terminating a Construction
Contract
Sometimes, of course, you have to terminate despite
the risks.
If you’re in that situation here are our practical
tips and questions to ask along the way:
1. Know your contract – what does it say about
termination, about losses, and about the situation that you are faced with?
2. Why do you want to terminate the contract? What
is it that has caused you to think that termination is the best option?
3. Are there legal grounds to terminate either under
the contract or at common law (you might need advice on this)?
4. What process does your contract set out for
termination, if any?
5. What are your risks if something goes wrong and
the other party claims you have wrongfully terminated?
6. Are there other realistic options to termination
that have lower risks or exposure which can give you a palatable outcome?
As always, we’re here to help you – if you’re faced
with a termination problem, don’t hesitate to get in touch to work through the
issues.
Termination in construction contracts .
Variations. Last edited 06 Feb 2018Posted by John P.
Ahlers
On January 16, 2014
In Construction News and Notes , Contracting ,
Government Contracts , Notice Issues Construction Contracts Termination Basics
– Part II
This is the second post in a two-part blog
addressing construction contract terminations. Read our previous post on
“Terminations for Convenience” here .
B. Termination for Default
Termination for default is a draconian action. It
constitutes a type of forfeiture; therefore, courts scrutinize terminations for
defaults carefully to ensure that the contractual provisions the parties agreed
to as part of their original bargain are followed to the letter. The impact of
a termination for default is a cessation of revenue by the contractor or
subcontractor for the specific project. The terminated contractor or
subcontractor may be accountable for reprocurement costs and other damages.
Generally, because default terminations are forfeitures, Courts regard them
with disfavor.
A typical termination for default clause reads as
follows:
Termination for Default. If Subcontractor refuses or
fails to supply enough properly-skilled workers or materials to maintain the
schedule of Work, refuses or fails to make prompt payment to lower-tier
subcontractors or suppliers of labor, materials or services, fails to correct,
replace, or re-execute faulty or defective Work done or materials furnished, disregards
the law, ordinances, rules, regulations or orders of any public authority
having jurisdiction, files for bankruptcy, or is guilty of a material breach of
this Subcontract, and fails to correct the default and maintain the corrected
condition within not less than three (3) working days of receipt of written
notice of the default, then Contractor, without prejudice to any rights or
remedies otherwise available to it, shall have the right to any or all of the
following remedies:
(1) Supply such numbers of workers and quantity of
materials, equipment, and other facilities as Contractor deems necessary for
the completion of Subcontractor’s Work, or any part thereof, which
Subcontractor has failed to complete or perform after the above notice, and to
charge the cost thereof to Subcontractor who shall be liable for the payment of
same including reasonable overhead and profit.
(2) Contract with one or more additional
subcontractors to perform such part of Subcontractor’s Work as Contractor shall
determine to provide prompt completion of the Project and charge the cost
thereof to Subcontractor.
(3) Withhold payment of any monies due or to become
due Subcontractor pending corrective action to the extent required and to the
satisfaction of Contractor.
(4) Terminate this Subcontract, use any materials,
implements, equipment, appliances, or tools furnished or belonging to
Subcontractor to complete Subcontractor’s Work and furnish those materials,
equipment, and/or employ such workers as Contractor deems necessary to maintain
the orderly progress of the Work: Subcontractor’s equipment shall only be
utilized when equivalent equipment is not locally available to lease, will not
be supplied by a substitute subcontractor, and when procurement of substitute
equipment will delay completion of the Main Contract. All of the costs,
including reasonable overhead, profit and attorneys’ fees, incurred by
Contractor in arranging to and performing Subcontractor’s Work shall be charged
to Subcontractor and Contractor shall have the right to deduct such expenses
from monies due or to become due Subcontractor. Subcontractor shall be liable
for the payment of any expenses incurred by Contractor in excess of the unpaid
balance of the Subcontract Price.
In the event of any emergency, Contractor may
proceed as above without notice.[1]
Generally, a termination for default clause contains
the following elements:
Definition of Default. The default provision
contains certain grounds for a default termination. Most common are the failure
to meet the completion date; failure to make progress; failure to make payment
to subcontractors, lower-tier subcontractors, and suppliers; failure to repair
or replace faulty or defective work; disregard of laws, ordinances, rules, or
other regulations; filing for bankruptcy; or otherwise materially breaching a
term of the contract/subcontract.
Cure Notice. The second feature of a well-written
termination clause is a cure notice. Generally, the contractor/subcontractor is
given a period of time (3 to 5 working days) to cure the default after being
provided with written notice of the event giving rise to the termination. A
properly-crafted termination letter includes the specific bases for the
default, the specific cure demanded of the contractor or subcontractor, and
complies with the cure notice duration in the contract to the letter.
Default Remedies. The third feature of the
well-written default provision is that the default remedies are set forth with
particularity. Among the default remedies are augmentation of the
contractor/subcontractor’s work through engagement of other workers or
subcontractors, subcontractor’s withholding of money, and ultimately the
termination and takeover of the contractor’s work.
Although not expressly stated in the standard
default clause, closely-related concepts of contractor anticipatory repudiation
or abandonment provide additional grounds for default termination. If a
subcontractor or contractor leaves the project without any intention of
returning, that constitutes an “abandonment,” which allows the owner/general
contractor to take over the contractor’s/subcontractor’s work. To show that the
contractor or subcontractor has abandoned the project, you must demonstrate an
affirmative, unequivocal, and unconditional declaration of intent not to
perform or some other unequivocal, definite demonstration of intent not to
return.
The existence of a technical default by the
contractor/subcontractor does not necessarily mean that a default termination
is proper. Wrongful termination is itself a breach of contract. It relieves the
contractor/subcontractor’s liability for preceding breaches and discharges the
surety of any obligation under its performance bond. The owner or general
contractor bears the burden of proof with respect to whether the termination
for default was justified regardless. A default termination is a drastic remedy
that should be imposed only for good grounds on solid evidence.
Comments: Termination is a tricky area of the law of
contracts. Contractors and subcontractors are well advised to involve legal
counsel before undertaking a contract termination, as the facts and
circumstances of construction defaults vary widely and are oftentimes both
factually and legally complex. Given the potentially harsh results, including
the consequences of the default termination and the death sentence that the
default termination suggests, it is prudent to contact an experienced
construction lawyer at the first sign of trouble, and certainly before taking
the extreme action of terminating a construction contract.
[1] Associated General Contractors of Washington
Subcontract Form (2009).
0 comments on Construction Contracts Termination
Basics – Part II PREVIOUS POST NEXT POST
Copyright © Ahlers Cressman & Sleight PLLC - All
Rights Reserved TERMS OF USE | PRIVACY POLICY | LEGAL DISCLAIMER
206-287-9900
999 Third Avenue, Suite 3800
Seattle, WA 98104 Last modified : 02/02/18 Author :
Law student
Disclaimer: This work has been submitted by a
student. This is not an example of the work produced by our
Law Essay Writing Service . You can view
samples of our professional work here .
Any opinions, findings, conclusions or
recommendations expressed in this material are those of the authors and do not
necessarily reflect the views of LawTeacher.
Does the doctrine of frustration have a useful and
coherent role to play in English contract law?
Introduction
‘Discharge’ is the technical name for bringing
contractual relations to an end. A contract can be discharged in one of four
ways. The main one is Frustration.
‘Frustration’ is an event that occurs outside the
parties’ control, which prevents the contract from being carried out
Frustration under English law is a doctrine, which
acts as a device to discharge contracts where an unexpected event either
transmutes contractual obligations impossible, or drastically modifies the
party’s initial purpose for entering into the contract.
The common law doctrine of Frustration comes into
play to discharge contractual obligations when no party is at fault. What
actually happens is that an intervening event occurs that disables the
performance of a contract. This event turns performance physically,
commercially or legally impossible or transforms the obligations of the
contract profoundly different from those, which were agreed at first place.
With a first sight, it would seem that there is a
clear picture; frustration will take place in rare occasions falling under
those specific categories. However, no clear-cut list of events leading to
frustration exists. In addition to this the doctrine has been developed on a
case-by-case approach. Therefore, it is far from clear as to what equals to a
frustrated contract.
Indeed, when the doctrine should apply is a very
contrasting topic. Today the subjective implied term theory has been replaced
by the objective ‘reasonable man’ hypothesis. The main issue rests with the
courts. They are the one who will decide when an exterior event equalled to
sufficient frustration and proceed in the discharge of the contract. It is a
fact that courts nowadays show reluctance in discharging contracts as
frustrated.
There have been five theories[1] developed over the
years attempting to set in order this area. However if we want to identify the
peculiarities of its purpose in modern contract law we need to follow the
development this doctrine.
Frustration: a struggle to categorize the doctrine
However we may argue that Frustration in modern
contract law operates under three comprehensive categories. The basic factor is
an intervening act, which makes performance impossible, illegal or commercially
sterile.
Thus, Frustration is created by the impossibility of
a contract. This means that supervening events occur that may render impossible
the performance in occasions that involve a definitive damage of the subject
matter [2].
However if the subject matter is damaged that does
not necessarily mean that it will frustrate a contract. The risk of loss is an
important element that should be taken into serious consideration.
This point can be mirrored in the following example:
A has agreed to install an oven in B’s bakery, if, before the work was completed,
the bakery is destroyed the contract is frustrated but if only the oven is
destroyed, A is obliged to redo the work without any obligation from the other
party.
Impossibility also occurs by the death or illness of
a party, outbreak of war, strikes etc.
Subsequent illegality is another factor that can
frustrate a contract. This happens when parties are ready to perform but
changes in the law prevent it, such as the law in another country changes or
the law changes due to an outbreak of war [3].
The third scenario, which leads to frustration, is
commercial sterility; this arises when the central purpose of the contract is
destroyed unless substantial purpose remains.
Supervening events, which may equal in frustrating a
contract, will not necessarily occur to this result, since certain features may
omit the doctrine of frustration.
Provisions of Contractual Relationships
The common law relating to frustration leads to
‘dead or alive’ practices. If the doctrine applies, the contract is considered
as a dead one; if it does not apply the contract sustains all its legal
effects. The parties though may decide to agree on middle solutions.
For example, as far as the coronation seat cases are
concerned, the contracts provided that, if the processions were postponed, the
tickets should be valid for the days on which the procession eventually did
take place; or that the ticket holders should get their money back less a sum
to cover the other party’s expenses.[4] When the coronation was postponed,
these provisions effected in order to exclude the doctrine of frustration.
If a contract contains an express clause, which
specifically covers the casus, it is questionable whether or not the provision
covers the events, which have occurred.[5] In one case a contract to build a
reservoir in six years provided that the builder should have an extension of
time for delays ‘however occasioned’. This provision was interpreted as giving
him a period of grace only in the event of non-frustrated delays. It did not
cover the delays that had actually occurred when the First World War brought
the work to termination, and forced the builder to sell his construction plant.
The builder’s plea of frustration succeeded.
Also, the fact that the contract makes some
provisions for a supervening event will not exclude frustration if the
provision is incomplete. A charter party may, for example, provide that the
ship owner is not liable for delays due to certain events outside of his power.
A clause like the above will not prevent the charterer from founding a ground
of frustration. This happens because the provision deals only with one possible
effect of the delay, explicitly its result on the liability of the ship owner
for breach. It clearly does not contain anything about the liabilities of the charterer,
which can consequently be discharged as a result of frustration.
A contractual provision for the event will not
exclude frustration in certain cases of supervening illegality. Setting an
example, if one of the contracting parties becomes an alien enemy the contract
would not be saved by even the clearest obvious provision for that event; for
the parties cannot ‘contract out’ of the predominantly strong public policy
against aiding the enemy economy in time of war. On the other hand, clauses
dealing with export or import prohibition [6] are commonly supported that they
assume that the prohibition will be observed and do not subvert its purpose.
To conclude there is the possibility that a contract
may particularly provide for discharge on the occurrence of listed events,
whether or not these events generate a change of circumstances that would be
sufficiently essential to frustrate the contract. Such clauses are meant to
decrease the uncertainty which can result from the struggle to decide whether
the change is of this kind: and also to moderate the hardship which a party may
suffer where the damage is not ultimate so that he would stay bound even though
the contract has become unpredictably burdensome on him. If the specified event
occurs, the contract is discharged under the express term and not the doctrine
of frustration.
‘Self-induced’ frustration
Neither party can rely on ‘self-induced’ frustration
that is on a hurdle to performance raised by default or deliberate act of one
of the parties.[7] This is most obvious where that conduct constitutes itself a
breach of the contract. The venture may be discharged but the person whose
conduct induced the casus will stay contractually liable.[8] Therefore, he is
in breach of contract guiding the ship to war zone, resulting in her detainment
and cannot rely on the detention as a ground of frustration. The doctrine
similarly does not apply where the breaches of both parties contribute to a
frustrated delay. Neither can a party rely on an event which was due to his
liberate act, even though that act is not itself a breach. E.g. an actor who
had contracted to give a theatrical show on an indicated day could not rely on
failure to perform due to his imprisonment. Even negligence in bringing on the
incident would normally omit frustration. The defendants in Taylor v Caldwell
would not have been able to rely on the doctrine if the fire was caused by
their own negligence.
Following this principle the position ought to be
the same where a singer was unable to perform because he did not take care and
contracted flu; but as the effect of such conduct on a persons’ health is hard
to predict it may be that the contract could be frustrated in such a scenario.
The purposefulness of the rule that a party cannot
rely on self-induced frustration is to deprive the party of the benefit of the
doctrine of discharge; the rule must not result to prejudgment of the other
party. It follows that the party whose conduct has brought about the event
cannot rely on it as a foundation of discharge. However, the other party may be
able to do so. E.g. an employee who is prevented from working by a sentence of
imprisonment cannot be based on this fact and frustrate the contract. However,
his employee could rely on it, with the result that he would not be liable for
unjust firing.
The question whether frustration is indeed due to
the voluntary act of a party can also arise where A enters into several
contracts with different parties and the supervening event deprives him of the
power of performing some, but not all, of those contracts. Suppose A has
planted a crop of vegetables in a farm, which is normally expected to produce
20 tons. He agrees to sell 10 tons of this expected crop to X and 10 tons to Y;
but as a result of events beyond his control, the total yield is only 10 tons.
One view, for which there is considerable support in the authorities that if A
delivers the 10 tons to X, his contract with Y will not be frustrated since his
failure to perform it was due to A’s voluntary act; and that for the same
reason his contract with X would not be frustrated if he delivers the 10 tons
to Y. Yet it seems inconsistent with the principle of frustration to hold A
liable for a shortfall due to an event beyond his control, which would have
provided him with an excuse if he had agreed to sell the whole quantity to only
one buyer. As long as A acts reasonably in allocating the actual yield (in
delivering the 10 tons to the first of the two buyers to have contracted with
him) he should be under no further liability. It might also be reasonable for
him to allocate 5 tons to each buyer. He could then rely by way of excuse on an
express contractual provision for the event, but probably not on the common law
doctrine of frustration, since the effect of that doctrine is generally said to
be to bring about the total discharge of the contract.
Foreseen and foreseeable events: Risk and
Frustration
In many frustration cases, the courts have
underlined the unexpected nature of the supervening event. Herein, there can be
no frustration if, at the time of the contracting, the parties actually foresaw
that the event would, or was very possible to occur. This view is based on the
hypothesis that, in these circumstances, the parties accepted a possible risk
that the event may arise.
Such a risk would undoubtedly be mirrored in the
contract price; and if the parties did not want to take the risk, they could
clearly avoid it. To strengthen this argument, it is necessary to define
exactly what the parties foresaw. The fact that they anticipated a delay does
not prevent frustration if the delay that took place was of an absolutely
different order or magnitude and was not predicted.
Neither is the doctrine of frustration eliminated
merely because a party could have foreseen that the event would occur. No
doubt, it was ‘reasonably foreseeable’ that King Edward VII might fall ill at
the time fixed for his coronation, but this did not prevent the doctrine of
frustration from applying in such a case.
Several judicial statements support a more strict
method and assert that a contract can be frustrated even by an event, which was
perfectly foreseen. It is hard to understand why the courts should alter the
contractual dangers, which have been deliberately undertaken; and the desirable
view seems to be that, if parties contract with reference to risk of which they
were aware then they should normally be able to rely on the doctrine of
frustration.
They should be able to do so only if the contract
specifies that they had not intended to provide for the risk. For example they
could claim that, if such an event occurs, they would leave the legal experts
to sort it out and if their efforts to do so ended in deadlock, the contract
could indeed be frustrated.
Conclusion
The doctrine of frustration seems to become more and
more rare in the courts of England. Since the frustration of contracts is
highly restricted, a defense in frustration of a contract is highly unlikely
because the key element is that a valid contract has been made and the good
faith it has been structured upon should be under respect.
RELATED CONTENT
Future Stars Investment (U) Ltd v Nasuru (CIVIL SUIT
No. 0012 OF 2017) [2017] UGHCCD 138 (30 October 2017);
Arch Katerega & Anor v Uganda Posts Ltd
(HCT-00-CC-CS-0020-2010) [2012] UGCOMMC 83 (12 July 2012);
Ogugua & Anor v Mania (CIVIL SUIT No. 0013 OF
2012) [2017] UGHCCD 93 (20 July 2017);
Waga Vs The Cheif Administrative Officer Maracha
& Anor (CIVIL SUIT No. 0005 OF 2016) [2017] UGHCCD 153 (30 November 2017);
Mohammed Saru v Jinja Central Division Council (HIGH
COURT CIVIL SUIT NO 223 OF 2009) [2012] UGCOMMC 95 (17 August 2012);
ULII is a member of the global Free Access to Law
Movement and of the
African LII community : Headnote and flynote
Download
Search Summary:
THE REPUBLIC OF UGANDA
IN THE HIGH COURT OF UGANDA SITTING AT ARUA
CIVIL SUIT No. 0007 OF 2013
1. CAFE TECHNICAL SERVICES LTD. }
2. WOBAS CONSTRUCTION (U) LTD. }
…………………… PLAINTIFFS
A.
J. W. OPOLOT CONSTRUCTION (U) LTD. ……………………………
DEFENDANT
Before: Hon Justice Stephen Mubiru.
JUDGMENT
The plaintiffs jointly sued the defendant for
general and special damages for breach of contract. It was the plaintiffs' case
that on 23 rd January 2012 and subsequently on 15 th October 2012, they were
respectively sub-contracted by the defendant to offer services which included
supervision of the construction of classroom blocks and construction of a five
stance water borne toilet at Arua Public Secondary School respectively. The
agreed contract price for the supervision was shs. 25,000,000/= while that of
construction of the five stance borne toilet was shs. 18,000,000/=, and supply
of 10,000 concrete blocks at shs. 30,000,000/=. The second plaintiff was as
well required to pay to the defendant a sum of shs. 20,000,000/=, hence making
the whole contract price to be shs. 140,000,000/=. It is the plaintiffs' case
that due to the defendant's breach of the head contract, the defendant was
given notice of termination on 9 th March 2013 and the head contract was
eventually terminated on 10 th April 2013.
By the time of termination of the head contract, the
second plaintiff had made 7,000 blocks worth shs. 21,000,000/= at the rate of
shs. 3,000/= each. After the head contract was terminated, the defendant
instructed the second plaintiff to level and remove the top loose soil at the
costs of shs. 23,000,000/= The second plaintiff's total claim is shs.
64,000,000/= inclusive of the commitment fee of shs. 20,000,000/= while the
first plaintiff's claim is for shs.25,000,000/= hence a total of shs.
89,000,000/= is claimed by both plaintiffs against the defendant.
In its written statement of defence, the defendant
denied both plaintiffs' claims. It contended that the first plaintiff was to be
paid after completion of works but it failed to. It denied having stopped the
second defendant from making more blocks and instead level the ground, which
was never part of the contract. The defendant instead counterclaimed against
the first plaintiff a sum of shs. 5,000,000/= made to it as advance payment to
mobilise construction material and deposit the same on site which the first
plaintiff failed to do resulting in the termination of the head lease. The
defendant therefore counterclaimed for general and special damages for breach
of contract, interest and costs.
When the suit came up for hearing, the defendant was
unrepresented in court a return of service on court record that showed the
defendant had been served. There being no explanation for the defendant's
absence, the plaintiffs were granted leave to proceed ex-parte.
P.W.1, Mr. Tatia Allan, testified that the first
plaintiff is a company limited by shares and its major activities are
undertaking construction works and supply of various items like furniture,
building materials, equipment, etc. 23 rd January 2012, the first plaintiff was
sub-contracted by the defendant to supervise construction of classroom blocks
and a five stance water borne toilet at Arua Public Secondary School. The
agreement stipulated that the plaintiff was supposed to supervise the
construction of classroom blocks and toilets (the whole works). The work was
supposed to be done by workers employed by the defendant. The duration of the
work was for 48 weeks. Work commenced in August 2012 and the agreed
remuneration was shs. 25,000,000/= after completion of the work.
The plaintiff executed its work for about five
months. However, the contractor eventually failed to supply materials for the
works to the second plaintiff which was the company executing the works. The
defendant's contract was consequently terminated by Arua Public Secondary
School. There was no provision of termination in the agreement we made with the
defendant. The first plaintiff's role was to ensure that the approved plans
were being followed in execution of the works, overseeing the testing of
materials at the UNRA Lab in Arua, ensure that the materials used are of proper
quality, ensure quality workmanship, including the qualification of workers,
and their physical activities on the site e.g setting out of the buildings, the
tools that were being used and prepare progress reports from time to time. In
performing its duty, the first plaintiff guided by specifications given by the
Ministry in the copies of the bills of quantities. The first plaintiff was
based on site daily. It had about five employees of the company at the site
daily. The first plaintiff was supposed to be paid 25,000,000/= for that work
but the money was not paid since it suddenly lost touch with the defendant,
hence the suit.
P.W.2, Ms. Zulaika Ali, the Manager of the second
plaintiff., testified that the defendant is a construction company which
sub-contracted the second plaintiff to construct a five stance waterborne
toilets and supply 10,000/= concrete blocks. Before the second plaintiff
started work, it paid shs. 20,000,000/= as commitment fee to the defendant on
15 th October 2012. The defendant was supposed to pay the second plaintiff
140,000,000/= upon the execution of the work. The second plaintiff executed
part of the work but was never paid. the second plaintiff was unable to compete
the work because the head contract between the defendant and Arua Public
Secondary School was terminated before completion. The defendant was given
notice of termination on 9 th March 2013 and the head contract was eventually
terminated was on 10 th April 2013. By the time of termination, the second
plaintiff had made 7,000 blocks worth shs. 21,000,000/= at the rate of shs.
3,000/= each.
After his contract was terminated, the defendant
instructed the second defendant to level and remove the top loose soil at the
cost of shs. 23,000,000/= , which the second plaintiff did, hence the total
claim is shs. 64,000,000/= including the commitment fee. The second plaintiff
demanded for payment but it has never been paid. When the head contract was
terminated, the defendant left in the second plaintiffs' custody, a van and a
tipper lorry. The van is in custody of the first plaintiff while the second
defendant has the lorry. The Director of the defendant left the vehicles with
the plaintiff in the year 2013 promising he would come back to pay, but has
never showed up since then. The second plaintiff thus seeks to recover shs.
64,000,000/=, general damages for breach of contract and the costs of the suit.
P.W.3 Mr. Ayub Khan, the Site Foreman of the second
plaintiff testified that the second plaintiff excavated a pit about ten meters
by six metres for the construction of the waterborne toilet. They started by
demolishing the old structure, which was a block of three classrooms, during
late August and early September 2013 using an earth mover. They later removed
the loose soil around. They secured a machine for making concrete blocks and
installed it. They ferried stone dust and the work of making blocks kicked off
in October 2012. They produced around 7,000 blocks but were producing below
capacity because of limited space and the weather was not conducive because it
was a rainy season. They laid the foundation on the five stance waterborne
toilet. They were unable to compete the work within the contract period because
the machines were delivered late from where they were hired and they would
break down often. The works executed by the second plaintiff have not been paid
for as agreed, hence the suit.
In his written final submissions, counsel for the
plaintiffs Mr. Henry Odama in summary argues that both plaintiffs have proved
the execution of valid sub-contracts with the defendant. They have also adduced
evidence proving that they executed work under those contracts for which they
have not been remunerated by the defendant. They are therefore entitled to an
award of general damages for breach of contract, special damages of shs.
64,000,000/=, which were specifically pleaded and proved, interest on both
awards and the costs of the suit.
Although the defendant in this suit did not offer
any evidence, the plaintiffs still bear the burden to prove their respective
cases on the balance of probabilities since the burden was always on the
plaintiff to prove his case on the balance of probabilities even if the case is
heard on formal proof (see
Kirugi and another v. Kabiya and three others [1987]
KLR 347). The issues for determination are as follows;
1. Whether there exists valid contracts between the
plaintiffs and the defendant.
2. Whether the defendant breached any of those
contracts.
3. Whether any of the plaintiffs is entitled to the
reliefs sought.
First issue: Whether there exists valid contracts
between the plaintiffs and the defendant .
During his testimony, P.W.1, Mr. Tatia Allan
mentioned a contract dated 23 rd January 2012 but it was never tendered in
evidence. Under section 10 (2) of The Contracts Act, 7 of 2010, a contract may
be oral or written or partly oral and partly written or may be implied from the
conduct of the parties. From the testimony of this witness, it was established
that the first plaintiff entered into a contract with the defendant and that
the plaintiff executed a part of the contract.
During the testimony of P.W.2 she tendered in
evidence a contract dated 15 th October 2012 which was received and marked as
exhibit P. Ex. 4. Having examined both contracts, I find that the basic
requirements of validity, i.e.; valid offers met by valid acceptance, an
intention by both parties to create legal relations, certainty of the terms
agreed upon, valuable consideration given by both parties and capacity to
contract, are satisfied. None of the contracts is affected by any illegality or
other voiding circumstances. The first issue is therefore answered in the
affirmative.
Second issue: Whether the defendant breached any of
those contracts.
A breach occurs when a party neglects, refuses or
fails to perform any part of its bargain or any term of the contract, written
or oral, without a legitimate legal excuse. This includes failure to perform in
a manner that meets the standards of the industry or the requirements of any
express or implied warranty. Under each of the contracts, the defendant was
obliged to pay the respective plaintiffs for their service; with regard to the
first plaintiff, for supervisory services and with regard to the second
plaintiff, with regard to construction of a five stance waterborne toilet and
supply of 10,000 concrete blocks. There is no evidence that the defendant paid
for any of those services.
It is an implied term in every construction contract
that the contractor will carry out work in a "good and workmanlike
manner" (see
Duncan v. Blundell (1820) 171 ER 749; Cousins v.
Paddon 150 Eng. Rep. 234 (1835); Conquer v. Boot [1928] 2 KB 336, [1928] All ER
120 and
Purser and Co. (Hillingdon) Limited v. Jackson and
Another, [1971] 1 QB 166). This term imposed upon the plaintiffs an obligation,
during the performance of their part of the contract, to employ that degree of
skill, efficiency and knowledge which is possessed by those of ordinary skill,
competency and standing in the particular trade or business for which they as
sub-contractors were employed, preformed in a manner generally considered
proficient by those capable of judging such work. The focus is not on the
result of the work, but the manner in which the work was performed.
The first plaintiff undertook to complete the task
within a period of 48 weeks from the signing of the contract, hence by 24 th
December 2012. However, the head contract was terminated on 10 th April 2013
before the works under the first plaintiff's supervision could be completed.
With regard to the second plaintiff, the contract period was unspecified but by
10 th April 2013, approximately six months after the signing of their contract,
out of the 10,000 blocks contracted, they had produced only 7000 blocks. The
implication is that they were producing an average of 1000 blocks per month or
approximately 30 blocks a day or 4 blocks an hour, assuming they operated an
eight hour working day. The second plaintiff attributed this low productivity,
to faulty machines, bad weather, interruption by ongoing school activities and
limited space. None of these is a frustrating event capable of excusing the
second plaintiff from executing its part of the bargain. None of the reasons
will excuse the second plaintiff from liability for delay or non-performance of
its obligations.
Frustration of a contract takes place where there
supervenes an event (without default of either party and for which the contract
makes no sufficient provision) which so significantly changes the nature (not
merely the expense or onerousness) of the outstanding contractual rights and /
or obligations from what the parties could reasonably have contemplated at the
time of its execution that it would be unjust to hold them to the literal sense
of its stipulations in the new circumstances; in such case the law declares
both parties to be discharged from further performance (see National Carriers
Ltd v. Panalpina (Northern) Ltd, [1981] AC 675, [1981] 1 All ER 161).
Generally, these are events beyond the parties' control, which could not have
been foreseen at the time the contract was entered into or prevented by the
affected party. Thus, the fact that a contract has become uneconomic or
commercially impractical will likely not be considered a force majeure event
unless expressly provided for.
In the first place, there is no implied term for a
builder of a school to have uninterrupted possession of and access to the site
(see
Porter v. Tottenham U.D.C [1915]1K.B. 776 ).
Secondly, inclement weather, if at all it occurred, which fact was not proved
during the trial of this case, could not excuse the delay. For example in Davis
Contractors v. Fareham UDC [1956] AC 696, the plaintiff agreed to build 78
houses in eight months at a fixed price. Due to bad weather, and labour
shortages, the work took 22 months and cost £17,000 more than anticipated. The
builders said that the weather and labour shortages, which were unforeseen, had
frustrated the contract, and that they were entitled to recover £17,000 by way
of a
quantum meruit. The House of Lords held that the
fact that unforeseen events made a contract more onerous than was anticipated
did not frustrate it.
It is a well-established rule that where a party
agrees to do a certain thing, and does not specify how it shall be done, the
law implies a promise on his part to do it in the usual manner (see
Hattin v. Chase 33 A. 989 at 658 (Me. 1895 ). In the
instant case, at a production rate of only 30 blocks a day or 4 blocks an hour,
the second plaintiff cannot claim to have performed its part of the bargain in
a good and workmanlike manner. Similarly, the first plaintiff undertook to
supervise performance of the contract for a period of 48 weeks and 51 weeks
later, the works were yet to be accomplished. The first plaintiff too cannot
claim to have performed its part of the bargain in a good and workmanlike
manner. That notwithstanding, when the head contract was terminated, the
defendant assigned the second plaintiff additional work of levelling the site,
which was not part of the work the second plaintiff had contracted for
originally.
Improper performance provides a basis for finding
non-performance which may, in a proper case, not only discharge the recipient
of the services of its payment obligation, but also subject the service
provider to a claim for breach of contract. One party's failure to deliver the
quality of performance promised may potentially result in discharge of the
other party's performance obligation on account of failure of consideration.
However, it is only when the failure to perform in a workmanlike manner renders
the work of no value to the service recipient, that the latter's obligation to
pay for services is discharged. Otherwise, the plaintiffs would be entitled a
claim and the defendant a corresponding obligation to pay reasonable
remuneration for work done which is freely accepted, under the doctrine of
quantum meruit. In a quasi-contractual case such as
this, the court will look at the true facts and ascertain from them whether or
not a promise to pay should be implied irrespective of the actual views or
intentions of the parties at the time when the work was done or the services
rendered.
In British Steel Corporation v. Cleveland Bridge and
Engineering Co. Ltd, 1984] 1 All ER 504, [1984] 1 WLR 504, Goff J said:
The question whether.....any contract has come into
existence must depend on a true construction of the relevant communications
which have passed between the parties and the effect (if any) of their actions
pursuant to those communications. There can be no hard and fast answer to the
question whether a letter of intent will give rise to a binding agreement;
everything must depend on the circumstances of the particular case. In most
cases where work is done pursuant to a request contained in a letter of intent,
it will not matter whether a contract did or did not come into existence;
because if the party who has acted on the request is simply claiming payment,
his claim will usually be based upon a quantum meruit, and it will make no
difference whether that claim is contractual or quasi-contractual. Of course, a
quantum meruit claim (like the old actions for money had and received and for
money paid) straddles the boundaries of what we now call contract and
restitution; so the mere framing of a claim as a
quantum meruit claim, or a claim for a reasonable
sum, does not assist in classifying the claim as contractual or
quasi-contractual......As a matter of analysis the contract (if any) which may
come into existence following a letter of intent may take one of two forms:
either there may be an ordinary executory contract, under which each party
assumes reciprocal obligations to the other; or there may be what is sometimes
called an ‘if’ contract, ie a contract under which A requests B to carry out a
certain performance and promises B that, if he does so, he will receive a
certain performance in return, usual remuneration for his performance. The
latter transaction is really no more than a standing offer which, if acted upon
before it lapses or is lawfully withdrawn, will result in a binding contract.
The former type of contract was held to exist by Judge Fay QC in Turriff
Construction Ltd. v. Regalia Knitting Mills Ltd (1971) 9 BLR 20 ; and it is the
type of contract for which [Counsel for CBE] contended in the present case. Of
course, as I have already said, everything must depend on the facts of the
particular case; but certainly, on the facts of the present case – and, as I
imagine, on the facts of most cases – this must be a very difficult submission
to maintain.' If there is no contract there can be no question of a party to a
transaction being in breach of an obligation of the type which can only arise
under a contract. ‘In my judgment, the true analysis of the situation is this.
Both parties confidently expected a formal contract to eventuate. In these
circumstances, to expedite performance under that anticipated contract, one
requested the other to commence the contract work, and the other complied with
that request. If thereafter – as anticipated – a contract was entered into, the
work done as requested will be treated as having been performed under that
contract; if, contrary to their expectation, no contract was entered into, then
the performance of the work is not referable to any contract of which the terms
can be ascertained, and the law simply imposes an obligation on the party who
made the request to pay a reasonable sum for such work as has been done
pursuant to that request, such an obligation sounding in quasi-contract or, as
we now say, in restitution.
In the instant case, the work done by the second
plaintiff in levelling the site is not referable to the contract of
15 th October 2012, but was nevertheless done at the
request of the defendant. In the circumstances, the law imposes an obligation
on the defendant as the party who made the request to pay a reasonable sum for
such work as was done by the second plaintiff pursuant to that request. The
services offered by the two plaintiffs are not of a kind which would normally
be given free of charge. In absence of evidence suggesting that either
plaintiffs' failure to perform in a workmanlike manner rendered the work of no
value to the defendant, the defendant therefore breached its part of the
contract when it failed or refused to pay the plaintiffs a reasonable sum for
that part of the work as was done pursuant to the two contracts and the
subsequent request. The second issue is therefore answered in the affirmative
too.
Third issue: Whether any of the plaintiffs is
entitled to the reliefs sought .
Under section 61 (1) of The Contracts Act, 7 of
2010, where there is a breach of contract, the party who suffers the breach is
entitled to receive from the party who breaches the contract, compensation for
any loss or damage caused to him or her. For a loss arising from a breach of
contract to be recoverable, it must be such as the party in breach should
reasonably have contemplated as not unlikely to result. The precise nature of
the loss does not have to be in his or her contemplation, it is sufficient that
he or she should have contemplated loss of the same type or kind as that which
in fact occurred. There is no need to contemplate the precise concatenation of
circumstances which brought it about (see The Rio Claro [1987] 2 Lloyd's Rep
173).
On account of the plaintiffs' failure to prove that
their performance of their obligations under the contracts met the "good
and workmanlike manner" standard, their claim for general damages cannot
be sustained. Under the principle of ex turpi causa, the court will not assist
the plaintiffs to recover compensation for consequences that are partly out of
their own shortcomings. The claim for general damages for breach of contract is
thus rejected.
Although the plaintiffs are not entirely blameless
for the failure of the head contract and of their respective sub-contracts, the
circumstances are such that the law should, as a matter of justice, impose upon
the defendant an obligation to make payment of an amount which the plaintiffs
deserve to be paid, on a quantum meruit basis. The fundamental principle that
equity is concerned to prevent unconscionable conduct applies to a case like
this. The court will impose such an obligation where the defendant has received
an incontrovertible benefit (e.g. an immediate financial gain or saving of
expense) as a result of the plaintiffs' services; or where the defendant has
requested the plaintiff to provide services or accepted them (having the
ability to refuse them) when offered, in the knowledge that the services were
not intended to be given freely. The court regards it as just to impose such an
obligation on the defendant who has received the benefit and has behaved
unconscionably in declining to pay for it. The court is more inclined to impose
an obligation to pay for a real benefit obtained by the defendant, since
otherwise the circumstances will leave the defendant with a windfall and the
plaintiffs out of pocket.
The law is that special damages must not only be
specifically pleaded but must also be strictly proved. (See Kyambadde v. Mpigi
District Administration [1983] HCB 44 ). The plaintiffs not only pleaded the
special damages claimed but also adduced evidence proving them. The plaintiffs
are therefore entitled, on a
quantum meruit basis, to payment for their services,
and the value of that should represent the extent of the unjust enrichment
obtained by the defendant.
For that reason Judgment is entered for the
plaintiffs severally against the defendant in the following terms;
a. Special damages of Shs. 25,000,000/= in favour of
the first plaintiff.
b. Special damages of Shs. 64,000,000/= in favour of
the second plaintiff
c. Interest on the awards in (a) and (b) above at
the rate of 15% p.a. from the date of judgment until payment in full.
d. The costs of the suit.
Dated at Arua this 10 th day of July 2017
…………………………………..
Stephen Mubiru
Judge
10 th August ESSION MODERN DAY CONSTRUCTION
CONTRACTS
Facing frustration: the relevance of frustration in
modern day construction contracts
11 MAR 2016
— BY JANINE STEWART, PARTNER, AND
HANNAH GILLIES, SOLICITOR, MINTER ELLISON RUDD WATTS
Introduction
“Frustration of contract” immediately releases
contracting parties from performance of the contract if an event occurs beyond
their control which renders further performance “impossible” or “substantially
impossible”.
The test for proving that performance is
“impossible” is not straightforward and comes with a high threshold.
Furthermore , the application of frustration to modern day contracts, in
particular construction contracts, is questionable. This article examines the
doctrine of frustration and its continued relevance and application given that
various contracts (particularly property and construction contracts)
specifically address common frustration risk events.
The doctrine of frustration
The law of frustration is well settled in New
Zealand. As recently affirmed by the Supreme Court in Planet Kids v Auckland
Council (2014] 1 NZLR 149 (SC) at [51] citing Davis Contractors Ltd v Fareham
Urban District Council [1956] AC 696 (HL)), frustration occurs “wherever the
law recognises that without default of either party a contractual obligation
has become incapable of being performed because the circumstances in which
performance is called for would render it a thing radically different from that
which was undertaken by the contract”. In order for a contract to be
frustrated, the frustrating event must not be brought about by one of the
contracting parties, and the contract must not make provision for such an
event.
For example, in the High Court of Australia case of
Codelfa Construction Pty Ltd v State Authority of NSW (1982) 149 CLR 337 the
parties entered into a tunnelling contract for extension to Sydney’s rail
network on the understanding that the contractor’s price was based upon
continuous shift-working. This was reflected in the contractor’s programme,
which formed part of the contract. Shortly after work commenced, members of the
public obtained injunctions in order to restrict the contractor to two-shift
daytime working and no work on Sundays. On appeal from arbitration, the High
Court of Australia found that the arbitrator should have little difficulty in
holding that the contract had been frustrated given that the completion of the
works by the stipulated time for performance was impossible (without an agreed
variation to shifts).
High threshold
Once a contract is frustrated it is terminated
automatically and immediately, irrespective of the parties’ subjective
intentions to continue (albeit on modified or renegotiated terms).
Given that the effect of frustration is to end the
contract, the courts have been careful to confine the doctrine within narrow
limits and do not invoke it lightly, so as to not interfere with a negotiated
contract (Karelrybflot AO v Udovenko [2000] 2 NZLR 24 (CA) at [37]). Thus, the
doctrine requires that the contractual obligation becomes impossible or
incapable of performance.
This includes whether the purpose of the contract
has become impossible to attain (for example in Krell v Henry [1903] 2 KB 740
where the defendant leased a flat from the plaintiff for two days, and both
parties knew that the entire purpose of this was so that the defendant could
view the coronation procession of Edward VII. The procession was cancelled, and
it was held that the letting contract was frustrated). The result may have been
different if the court found that the viewing was not the sole purpose of the
letting contract and that the tenant would still have obtained some benefit out
of the contract.
It will not be enough that the obligation has become
more onerous, more expensive or slower (unless the delay is such that the
purpose of the contract is frustrated). Therefore, cases where the doctrine has
been successfully upheld in the construction context are usually of the kind
where the work in the project has been destroyed, for example by fire or
landslide (for example Appleby v Myers (1867) LR 1 CP 615).
The high threshold for a finding of frustration is
also influenced by the fact that contracting parties are expected to bear the
risk in contracts of certain kinds. So, for example, a contractor who provides
a quote for certain works is expected to take the risk that the works will
prove more difficult and more costly than expected.
In Davis Contractors (supra) shortages of labour and
materials meant that performance of a contract to build 78 houses in eight
months for £94,000 took 22 months and cost the contractor £115,000. Despite
such severe obstruction to contractual performance, the House of Lords found
that this was insufficient to frustrate the contract. The contractor had taken
on the risk of lack of labour because it was not an unforeseen event for a
contractor, and it could have been the subject of contractual stipulation if
the contractor did not want to take on this risk.
Remedies upon frustrating event
The Frustrated Contracts Act 1944 (FCA) contains two
major provisions to relieve injustice in a situation where one party has
performed their contractual obligations before the contract is terminated due
to a frustrating event.
The FCA provides that:
(a) Where money has been paid by one party before
the frustrating event, it can be recovered and monies payable cease to be
payable. If the party to whom these monies were paid has incurred expenses in
performing his or her part of the contract before frustration, the court may
allow him or her to offset a sum in respect of those expenses. For example, if
a contractor has partly constructed a house and has received $50,000 in
progress payments before the frustrating event, the owner will be entitled to
recover this sum less the amount the court allows the contractor to keep as
reimbursement for the works completed; and
(b) Where one party’s part performance has conferred
a benefit on the other party before the contract is discharged, that other
party may recover a “just sum” in compensation.
Parties can contract out of the FCA and specify what
will happen upon termination due to a frustrating event. For example, clause 14
of the standard form construction contract NZS3910 provides that:
“In the event that either the Principal or the
Contractor considers that the Contract has become impossible of performance or
has been otherwise frustrated, one may notify the other that it considers the
Contract to be terminated. If the other parties agree, or in the event of
disagreement if it is so determined by the Engineer or by mediation or
arbitration under Section 13, then 14.1.2 shall apply.”
This clause dictates the process if only one party
considers that the doctrine is engaged by referring it to the Dispute process
under clause 13 of NZS3910. If the contract is found to be frustrated, clause
14.1.2 provides for the costs that are payable by the principal to the
contractor following the frustrating events (including the value of the work
carried out at the date of termination less amounts previously paid).
In the context of construction contracts,
contractors and principals often find themselves in situations where
performance has become more onerous, more expensive or slower due to unforeseen
circumstances. However, the fact that the bargain has become unworkable in a
commercial sense because of an unforeseen event will not discharge the party
from further performance on the grounds of frustration. Therefore, it is
important that the contract is drafted to reflect the parties’ intention as to
what should happen if such an event was to occur and this is what a force
majeure clause is desired to do.
Force majeure clauses
Force majeure clauses are common in the construction
sector and offer a commercial mechanism to clearly address unforeseen events.
Parties can agree upon both the events that trigger the force majeure clause,
and the consequences. Unlike the strict doctrine of frustration, where the
threshold can be difficult to meet, parties can negotiate force majeure clauses
in order to achieve flexibility for certain events. For example, parties to a
construction contract may choose to suspend performance or extend time for
performance upon the occurrence of a force majeure event.
Clause 10.3.1 of NZS3910 is a force majeure
provision which provides that the engineer grant an extension of time to the
contractor if the contractor is “fairly entitled to an extension” including by
reason of flood, volcanic or seismic events, or any circumstances not
reasonably foreseeable by an experienced contractor at the time of tendering
and not due to the fault of the contractor.
Force majeure clauses are also included in the FIDIC
suite of contracts (Red, Yellow and Silver Books) at clause 19 where “force
majeure” is defined as an exceptional event or circumstance beyond a party’s
control, which could not reasonably have been provided against before entering
into the contract and which, having arisen, could not reasonably have been
avoided or overcome and which is not substantially attributable to the other
party. The categories listed as force majeure events include: (i) war and other
hostilities; (ii) rebellion, terrorism and civil war; (iii) riots and strikes
(by persons other than the contractor’s personnel and subcontractors); (iv)
explosive materials and radioactive contamination; and (v) natural catastrophes
such as earthquakes, hurricanes and volcanic activity.
Clause 19 of the FIDIC suite of contracts entitles
the contractor to an extension of time if it is prevented from performing the
contract by any of the force majeure events. However, it will only be entitled
to recover the costs incurred due to the force majeure event if it is a category
(i) to (iv) event (meaning that the contractor cannot recover costs arising in
relation to natural catastrophes).
Relationship between frustration and force majeure
Where the parties have turned their minds to the
frustrating event and contractually allowed for it in a force majeure clause,
reliance on the common law doctrine of frustration is generally precluded.
Given the prevalence of force majeure clauses in standard form construction
contracts, a finding that the contract had been frustrated in Codelfa
Construction Pty Ltd v State Rail Authority of NSW (supra) has been described
by
Hudson’s Building and Engineering Contracts (12th
Edition) as an “exceptional result” (at [1- 059]).
Force majeure clauses are commonplace in the
construction industry, such that the absence of one might be viewed as implied
acceptance of risk by the contractor for certain events that would normally be
covered by such a clause (and which therefore can no longer be described as
“unforeseen”). As was recently confirmed by the Supreme Court in Planet Kids
(supra) at [139]:
“Where risk is allocated to one of the parties under
the contract, then the doctrine of frustration is excluded, in so far as it
relates to the occurrence of one of the allocated risks. The allocation of risk
can be express or by necessary implication …” (emphasis added).
Determining whether a contractor has impliedly taken
on such risks in the absence of a clearly drafted force majeure clause will
obviously depend on the particular facts and circumstances. Some events, such
as earthquakes or other natural catastrophes, could be viewed as foreseeable
risks which should have been clearly allocated in construction contracts,
failing which the court may find that one of the parties has taken on the risk
by necessary implication, for example through being reflected in the agreed
price. In such a case, if the court finds the risk has been impliedly allocated
under the contract, the doctrine of frustration may be excluded.
However, there may be other scenarios where the court
determines that an event falls outside what the parties expressly allowed for
in a force majeure clause (or implicitly allowed for in the absence of such a
clause). In such a case, if it is not reasonable to place the risk of
non-performance for the events which have occurred on one party or the other or
neither, the contract may be frustrated.
For example, in Metropolitan Water Board v Dick Kerr
& Co Ltd [1918] AC 119 (HL) contractors entered into a contract in July
1914 to construct reservoirs at an agreed price within six years. In February
1916 the government prohibited the continuance of work due to the outbreak of
war. The contract provided the engineer power to extend time for completion in
the event of any “difficulties, impediments, obstructions,
oppositions…whatsoever and howsoever occasioned”. The House of Lords considered
that this scenario could not possibly have been in the contemplation of the
parties to the contract when it was made and therefore it fell outside the
scope of the force majeure clause. The contract was therefore frustrated as the
works were prohibited by law (at [126]).
Conclusion
The threshold for frustration is high, and the
operation of frustration will be contractually constrained by what the parties
have allowed for in their contract, in particular with reference to the force
majeure clause. Increasingly, parties are already allocating risks or at least
addressing some risks in their contract, such that the doctrine of frustration
often does not apply.
However, it is arguable that a well-drafted force
majeure clause assists the court in reaching a finding of frustration where
there has been a truly frustrating event, as the court can clearly identify
which risks the parties have foreseen and allocated accordingly.
How strong the doctrine of frustration will be in
modern day contracting will continue to be tested by (most commonly
unfortunate) catastrophic events.
Comments
Post a Comment